In order to initiate an INSPECTION, we require a completed REQUEST FORM and a check made out to “CTIOA Inc.” PRIOR TO SERVICES If applicable, please include a map of jobsite location with request.
INSPECTION FEE SCHEDULE
- STANDARD LOCAL INSPECTIONS, small projects less that 1000 sq/ft include
inspection of two (2) tile assemblies, approximately ONE (1) hour on project,
a written
report and photos.
See Daily rates for projects over 1000 sq/ft.
Note: Proper evaluation of existing work may involve removal of certain parts of the work.
CTIOA Inc. cannnot replace or be liable for removed portions of the work.
For projects in Los Angeles, Orange .................................................$525.00
For projects in Ventura, Riverside & San Bernardino, San Diego........$625.00
For projects in Las Vegas, Nevada.....................................................$625.00
For projects in Atlanta, Georgia..........................................................$625.00
For each additional tile assembly inspected, add .................................$250.00
For each additional hour at site............................................................$250.00
For large projects over 1000 sq/ft.......................................................Daily Rate
- OUT OF TOWN INSPECTIONS within the 50 United States includes:
(Portal to Portal) + all incurred expenses.…………………$2,000.00/Day
- INTERNATIONAL INSPECTIONS quoted on a case by case basis.
- MAIL – E-MAIL – FAX Send photos & verbal description
of job problem
(photo of exposed backing to which tile is adhered as well as type of substrate, i.e.
wood, backer unit type, concrete recommended.)
We will offer written opinion as to problem and make recommendation for repair if applicable.
For up to two (2) tile assemblies…………………………………………………$250.00
For each additionalassembly……………………………………………………..$100.00
If information is not enough to form an opinion, money & information will be returned.
- QUALITY CONTROL
Specification Writing – Case by case basis, per assembly, usually about………….$1,500.00
Pre-Job Meetings – same as inspection costs
Installation Monitoring – see hourly rates
Incurred expenses would apply for out of town work.
- RATES Per Person - (all Portal to Portal, plus expenses)
Large project and multi unit inspection ............................$2000.00/Per Day
Research, consultation, (hourly rates)...............................$250.00/hour
Arbitration, Deposition, Testifying/Waiting Time ..............$250.00/hour
48 hour:CANCELLATION NOTICE required or fee ...........$250.00
- THERMAL IMAGING..............................$
3000.00 per day + expenses
Bond Coverage Identified through the use of Infrared Technologies Presents a Non-Destructive
View of Adhered Veneers not Visible to the Human Eye.
- TRAVEL (Portal to Portal)
Travel to and from.....................................................................................................$200.00/hour
Travel starts from Inspector's Location. (Reason: Inspector may in fact spend more time traveling than consulting).
- FLOOR SAFETY TESTING
Coefficientof Friction ASTM C-1028
Lab test (3 samples)....................................$260.00
Field test (1 area)…………………………$850.00
Each additional area add…………………..$260.00
Surface Roughness
Lab test (3 samples)………………………$60.00
Field test (1 area)…………………………$650.00
Each additional area add…………………..$60.00
Tortus Test, dry and wet (3 samples)…………………$290.00
Pendulum Test, dry and wet (3 samples)……………….$290.00
Field test (1 area)……………………………………...$890.00
Each additional area add……………………………….$260.00
Coefficient of Friction
Arbitration, Deposition, Mediation, Testifying/Waiting Time…………….…$ 400.00/hour
Testing and consulting…………………………………………………….$ 250.00 hour
- Stain Testing
CTIOA Stain Test - T-72 (2 untreated samples)………………………………….$ 440.00
Field test prices good for Los Angeles, Orange, Riverside and San Bernardino Counties.
For San Diego and Ventura Counties add $200.00.
for out of area testing, call for quate 310-574-7800
NOTE
While our physical inspection of an installation may result in observation of deviation from Industry Standards, we do not form an opinion as to who or what may have caused such deviation. Although every effort will be made to make a complete inspection, certain critical parts of the workmanship and materials may not be observed due to the inherent limitations of an “after the fact” inspection.